This project consisted of the supply and installation of a 600×600 Zentia Seismic Rx Suspended Ceiling System, complete with the added technical complication of an 1800mm wide, 45 degree slope.
These works were carried out to the main operational control room of Hunterston B Nuclear Power Station, for EDF Energy.
The Seismic System installed, was required by the client to ensure that the ceiling installation would withstand forces associated with significant seismic activity or other severe events. This was to make certain that the Power Station remained fully functional and safe at all times.
Historically few installations of this nature are carried out in the UK. We are proud to have been involved in all aspects of this unique and highly specialised project.